Cart
Home/Task Analysis/Cladding & Weatherboards/New Cladding and Panel Installation

TA-CL-09 · Cladding & Weatherboards

New Cladding and Panel Installation Task Analysis

Craneage, handling and installation of new facade cladding and panels including fixing into the structure and weatherproofing details.

What you get

One editable Word document covering new cladding and panel installation for Cladding & Weatherboards: the task broken into steps, the hazards at each step, the controls, and a 5 by 5 risk matrix with residual ratings. Site fields and a crew sign-on are built in.

A Task Analysis is also known as a JSA (Job Safety Analysis) or JSEA. It covers each step of the job, the hazards and the controls.

The steps and hazards it covers

StepHazards
Plan, prepare and confirm competencyWorkers without the required training, competence or authorisation performing the task - incidents arising from lack of skill, competency or authorityDefective or unsafe plant, powered equipment, leads or attachments failing in use
Lift panels into positionSuspended panel lift failure or contact - fatal crush and strikes to persons below
Handle panels in windWind gusts catching panels during handling and placement - loss of control and falls from the work platform
Fix panels to the structureFixings installed into unverified substrate failing - panel detachment and falling panels
Manoeuvre panels near glazingPanels and lifting gear striking adjacent glazing - glass breakage falling to persons below
Cut and trim panels on siteSharp cut edges, rivet swarf and cutting tools - lacerations and metal slivers in hands and eyes
Coordinate the occupied building interfaceOccupants at openable windows and balconies adjacent to installation zones - injury from panels and tools at openings
Work in approved out-of-hours windowsNight and weekend installation windows - fatigue and reduced visibility errors at height
Demobilise and clean upPanel offcuts, protective film and packaging left on platforms and ground - falling objects and slips and trips

Each hazard comes with its control measures, an initial and residual risk rating and the person responsible, ready to check against your job.

How to use it

Read it against the actual job. Delete the hazards that are not there, add the ones that are, fill the site fields, then brief the crew and get every name on the sign-on. A document nobody has read is a piece of paper. One the crew helped finish supports worker consultation and records the agreed work method. Engagement under HSWA ss58 to 59 is an ongoing process of seeking and considering workers’ views, so the signed page is evidence of part of it rather than the whole duty.

About Cladding & Weatherboards Task Analysis

This is one of the Task Analysis documents written for Cladding & Weatherboards crews. The trade covers weatherboard, fibre cement and sheet cladding, cavity battens, flashings, soffits, work from scaffold.

See every Cladding & Weatherboards document, or the whole pack for $199.99. Need 5 or more templates from this trade? The pack costs less than buying them individually, and saves $49.96 at 5.

Where it sits in the law

New Zealand does not require a document of this name. The duty is to manage risk so far as is reasonably practicable (HSWA s36) and to engage workers on it (ss58 to 59). Use a Task Analysis to plan the work, identify the hazards and communicate the controls to your crew. That is also how you evidence both duties.

WorkSafe names “a task analysis, safe work method statement (SWMS), job safety analysis or equivalent planning document” as the same thing done under different headings, and Site Safe titles one of its own SSSP forms “Task Analysis (TA) and Safe Work Method Statement (SWMS)”. So if the paperwork you have been sent asks for a TA, a SWMS or a JSA, this is the document it means, written to the Health and Safety at Work Act 2015. Only the name changes; the hazards, controls and ratings are the same either way.

Where this sits in your SSSP

A Site-Specific Safety Plan (SSSP) covers the whole job: who is on site, how hazards get reported, what happens in an emergency. A Task Analysis covers one task inside it. They are not the same document. Site Safe’s SSSP pack runs to ten forms, and the Task Analysis is Form 10, filed behind the plan itself.

So a main contractor who asks which SSSP pack you are using, and then asks for a TA covering new cladding and panel installation, has asked you for two separate things. This is the second one. Keep it with your SSSP for the job and bring it to the pre-start briefing, because the value is in the crew having read it before the work starts.